What self‑performing actually buys you
Trillium acts as its own general contractor on most of what we build. People assume we do it for the margin, to keep the contractor’s fee. We do it to control costs and for speed to lease-up.
What it costs
You take on risk a general contractor would otherwise carry, and holding it yourself does not make it any smaller. You need people on payroll in a difficult labor market, between projects as well as during them, which is harder than hiring for a single job. And when a schedule slips, there is nobody else to point at.
That last one sounds like a soft cost, but much of running a large project is two parties keeping a record of who caused a delay. Removing the second party removes the argument. It also removes the person you were going to bill.
What you get
The return is speed of decision, and on the right kind of project that is worth more than the fee.
On an adaptive reuse project you will routinely open a wall and find something no drawing predicted. The building is thirty or forty years old, it has been modified by tenants nobody kept records of, and the as-builts describe a building that stopped existing some time in the 1990s. Since the surprises are certain, what you plan for is the hour after you find one.
With your own team, somebody walks over, looks at it and makes the call that afternoon. With a third party, the same decision goes into a meeting, then an RFI, then a change order, and each of those steps has a queue in front of it. The delay comes from the process itself, even when everyone in it does their job well. Third-party general contractors make a lot of their money on change orders.
Across a conversion, that difference is measured in months.
Why it matters more here than on a new build
I would not make this argument as strongly about ground-up construction. On a new build you are putting a design on an empty site. The unknowns sit in the ground and are mostly resolved before you go vertical, and a good contractor on a fixed price is a rational way to buy that.
Conversion inverts that. The unknowns run through the whole structure and surface continuously, from demolition to close-out. A contract that fixes a price at the start puts a number on something neither side can see yet. The number carries contingency, and the contingency gets spent arguing over whose it was.
We learned this at The Landon. It began as an office building and is now 160 homes: 62 apartments inside the original office structure, 20 build-to-rent units above the existing parking, and 78 more on adjacent land we picked up. We self-performed it to keep control of the decisions, and that is why the finished building resembles what we drew. We built a Class A product at two-thirds of what a new wood-frame build would have cost, saving more than $100,000 per unit.
Then you have to operate it
We also manage what we build, and that belongs in the same conversation because it closes the loop.
Building something and handing it to a third party to operate teaches you very little. You get a monthly report and a set of numbers that have already been interpreted for you. Operating it teaches you what you got wrong: which unit types sit, which finishes fail in year two, which amenity nobody uses, where the maintenance calls cluster, which floor plan the leasing agent has quietly stopped showing.
You learn it because your own people are the ones fixing it, and the next project is drawn by somebody who heard about it. On a conversion that feedback is worth a great deal, because there is a long list of decisions to make and convention settles almost none of them.
When I would not do it
If you are building one project, in a market you do not operate in, on a schedule that depends on trades you have no relationship with, hire a good general contractor. Self-performing is a capability you keep standing between projects, and it pays only if you keep the team busy and the work is the kind that generates surprises. Without both, you are buying overhead and calling it control.
The Landon and Canyon Corporate Plaza are on the projects page, with their unit counts and current status.